Land·Air·Water

Commercially led support for UK & international construction — from feasibility to final account.

Proactive risk mitigation, matched with prompt dispute advice — advisory support that adds to your commercial acumen across TIME · COST · CONTRACTS, through both phases of the project lifecycle. Serving the UK, Ireland, the EU, the GCC and Canada.

Standard forms, administered as signed NEC4 · JCT · FIDIC (1999 & 2017) · bespoke UK · Ireland · EU · GCC · Canada
Who we act for — three seats, one standard

Employer & Developer

From ERs to final certificate — the documents, the machinery and the record that protect the scheme.

Contractor & Supply Chain

From tender qualification to true value — entitlement built in real time, and defended.

Funder & Monitoring

From due diligence to drawdown to step-in — security that stays liquid because the record stays current.

One side per matter, always — every instruction is conflicts-checked, with the outcome confirmed within one working day.

Aligned with the market — differentiated where it counts

What only Quantico brings to the table

The combined time–cost schedule

  • Cost maturity and time maturity unified into one risk-managed instrument — the baseline that manages the site daily and defends the account later
  • Genuine added value at development and project-planning stage: one document, both dimensions, risk built in

Any-format schedule analytics

  • Deltek, Powerproject, MS Project and Primavera P6 imported and interrogated — forensics, scenario modelling, optimisation
  • Compliance reporting to DCMA, NASA, DfT, NEA and MoD frameworks — capability no claims consultancy advertises

The funder arc

  • Due diligence → independent auditing → restructuring support, one continuous thread for lenders and investors in real estate finance and investment
  • The same team that set the investment baseline monitors it while the money is at work

One working day

  • Every enquiry answered with a view and a next step within one working day — a responsiveness promise no benchmark firm makes
  • Phase selector and service pre-fill get you to the right conversation first time

The recourse architecture, read as one machine

  • Warranties and third-party rights, bonds and guarantees, insurance clauses and termination mechanics reviewed as a single recovery system — so when the contract is not enough, the next instrument is already identified
  • Registers kept live against the programme — who owes what, to whom, on which instrument, until when — with placement and coverage advice sitting where it belongs, with the client's authorised broker
Published fees. Shared risk. Small print you can actually read.Indicative fees are published on the site — starting points from the value stated, confirmed on scoping, beginning with a free 20-minute triage call.See the Fee Schedule →
Legislation watch — currency as a discipline

The statutory ground moves. The advice moves with it.

Major statutory shifts are monitored continuously, so every determination, tender review and claim position reflects the current law — not last year's.

Payment & adjudication

Construction Act 1996

Payment mechanisms, notices and pay-less positions, true-value adjudication, suspension rights — tracked through the evolving case law that decides them.

Building safety

Building Safety Act 2022

Gateways, duty-holder and competence requirements, and the golden thread — reflected in Employer's Requirements, appointments and contract administration.

Public procurement

Procurement Act 2023

The new public procurement regime — procedures, transparency notices and exclusion grounds — factored into procurement strategy and tender management.

Arbitration

Arbitration Act 2025

The reformed framework for England-seated arbitration — summary disposal, the governing-law default and recast court powers — reflected in arbitration support and multi-tier escalation strategy.

ADR & the courts

CPR ADR reforms — post-Churchill

After Churchill v Merthyr Tydfil, the courts can order parties into ADR — embedded in the CPR from October 2024. Mediation positioned early, before positions harden and costs sanctions bite.

Insolvency

CIGA 2020 — s 233B

Ipso facto protection for supplies: termination-on-insolvency clauses restrained in supply contracts — screened within termination support and supply-chain reviews before any election is made.

Standard forms — edition currency.The JCT 2024 suite and NEC4 amendment currency are tracked continuously, so administration and advice run on the edition actually signed — tracked at form level; clause commentary belongs in the engagement, not on the site.
Practice Notes & Insights

Forty-six practice notes. Four series. A fifth in preparation.

Thought-leadership at practice level — the disciplines that build and enforce the project record, published as four practice-note series. No clients, no projects, ever; the reading destination is LinkedIn.

10 papers

Adjudication Series

Statutory adjudication under the Construction Act 1996 — notices, jurisdiction, true value, enforcement.

12 papers

Delivery Series

The delivery-phase disciplines that create the record — baseline to final account.

12 papers

NEC Series

NEC4 ECC administered as machinery — programme, early warning, compensation events, W-option disputes.

12 papers

Recourse Series

When the contract is not enough — warranties, bonds, insurance clauses, insolvency and termination.

In preparation

FIDIC Series

The 1999 and 2017 Books run as machinery — Sub-Clause 20.2 claims, Engineer's determinations under 3.7, DAAB practice — for GCC and international work.

About us — mission · approach · team + the L.A.W. story

Our Mission

Empower stakeholders by proactively addressing risk to prevent cost overruns and delays — with robust structures ready to manage claims and resolve disputes.

Our Approach

A proactive service model across all phases, from risk assessment to dispute resolution — anticipate early, prevent complications, represent expertly when disputes arise.

Our Team

Seasoned professionals across project management, legal compliance and risk assessment — preventive strategies and practical solutions in balance.

Land · Air · Water

The elements behind the name reflect the legal divisions of the work: construction contracts; service and consultancy agreements; and commercial damages. A practice-area motif, not a map — service jurisdictions are stated separately: UK · Ireland · EU · GCC · Canada.

About·The Team & The Ethos

A multi-disciplined team. A declared standard.

Whoever you are — end user, developer, funder, design team, lawyer or contractor — the team assembles around your side of the table.

The disciplines we field

Nine disciplines, one table

Quantity surveyors — chartered-track, cost & contract Planners & schedulers — P6 / MSP / Powerproject Project managers Contract managers & administrators (NEC & FIDIC) Employer's Agents (JCT DB) Claims & forensic analysts — delay & quantum Adjudication-experienced — Party Representative capability Expert witness capability — quantum & programme Risk analysts — qualitative & quantitative
The ethos — four commitments

Decisive, timely advice

Advice arrives while it can still change the outcome — delivered cost-efficiently, framed for the decision at hand, never hedged into uselessness.

Currency as a discipline

Authority lines tracked, annual industry reporting reviewed, continuous professional development embedded — the advice is current because the practice is. The practice library is maintained against primary sources and the current editions of the leading protocols, standard-form suites and treatises, with a continuing update discipline.

Standards without compromise

Ethical, professional and technical standards held at the highest level on every engagement — the same rigour whether the matter is routine or existential.

Partnerships, not transactions

Long-term client relationships built on a deepening understanding of each client's projects, pressures and goals — the trusted-advisor seat, earned repeatedly.

Leadership credential — 30+ years UK, EU & GCC · JCT, NEC & FIDIC administration · LLM Construction Law & Practice · PMP · NEC4 · APMG · dual forensic diplomas (schedule + quantum) · Adjudication. Practice run to RICS and professional-body standards and guidance, adopted as voluntary best practice. Practice affiliations span landmark engagements — from major London commercial schemes to super-high-rise and PMC programmes in the Gulf — with client confidentiality preserved throughout.
Post Contract5 of 5·Expert Services

Expert Services

“Independent analysis that stands up to scrutiny.”

Forensic quantum and delay analysis, independent expert evidence and Earned Value insight — prepared to the standard the tribunal expects, and delivered by practitioners who have administered the contracts they now examine.

Acting for instructed party-side or as independent expert — never both in the same matter; conflict check within one working day

Independence

Independence, stated plainly.

When Quantico is instructed as an independent expert, our duty is to the tribunal — not to the instructing party, and not to Quantico's commercial interest. Expert evidence is prepared in accordance with Part 35 of the Civil Procedure Rules and its Practice Direction, the Civil Justice Council's Guidance for the Instruction of Experts, and — in arbitration — the CIArb Protocol for the Use of Party-Appointed Expert Witnesses, as the forum requires.

Because Quantico also acts party-side — in commercial management, claims preparation and party representation in adjudication — every prospective expert appointment is conflict-checked before acceptance. What you get in return is an expert whose opinions are formed the same way whichever side instructs them.

Two chairs, never both.

The law itself draws the line, and Quantico holds it: as claims consultants we prepare and prosecute the client's case; as independent expert our overriding duty is to the tribunal, under CPR Part 35 and CIArb standards. The two chairs are never occupied in the same matter — the conflict check enforces the line. You always know which chair is taken, and the tribunal always gets the duty it is owed.

The duties held on every appointment run wider than the dispute: the contract and its machinery; the liability matrix; limitation horizons; the insurance architecture and the security schedule; the delivery-phase record-building disciplines; endings; and every resolution forum — for employers, contractors and funders alike, conflicts checked.

Duty to the tribunal

CPR Part 35, CJC guidance and the CIArb protocol govern every instruction, whichever forum hears the matter.

Conflict-checked at first contact

Every prospective appointment is screened against current and past engagements before acceptance — and we tell you the outcome straight away.

Roles never mixed

Where we have advised a party, we will not accept an independent-expert instruction on the same dispute. Advisory and expert roles stay separate, always.

The expert you instruct

Lead Expert

Photo
to follow
Michael J Pratt
Quantum & Programme
LLM Construction Law & Practice Forensic diplomas — schedule & quantum NEC4 · PMP CIArb

Michael J Pratt is an expert quantum consultant & delay analyst with 30+ years across the UK, EU and GCC, spanning JCT, NEC and FIDIC administration on programmes to AED ~4.00bn in capital value. Appointments span adjudication, arbitration and litigation support, developed and defended for employers, contractors and funders alike.

£5.56m
True-value determination, prepared and sustained
£1.6m
Measured Mile disruption analysis
AED 4.00bn
Programme baseline under sole commercial authority
The offer — full service set

The full service set.

Forensic & Expert Evidence

  • Forensic quantum analysis — financials examined for discrepancies and unforeseen cost
  • Programme / delay analysis — causes pinpointed, impacts evaluated, evidence-based reports
  • Independent expert witness evidence in legal and arbitration proceedings

Dispute & Claims Support

  • ADR support — mediation and arbitration; case files prepared, clients supported to favourable settlement
  • Claim review & development — substantiated claims and robust defences grounded in evidence

Commercial Risk Support

  • Commercial risk assessment & management — financial and operational risks identified and managed
  • Mitigation via contractual amendment and risk-transfer options identified for review with the client's authorised broker

EVM & Project Data

  • Earned Value Management implementation to best-practice frameworks
  • Project variance reporting — scope, schedule and budget deviations assessed for timely correction
  • Performance insight safeguarding delivery against unexpected challenge

Forensic Products — Recourse & Recovery

  • Contribution and apportionment quantum for multi-party claims — each party's share modelled and defended
  • Defect-exclusion recovery modelling across the DE / LEG tiers — the quantum consequences of each tier priced; coverage itself stays with the client's authorised broker and legal advisers
  • Bond-call and termination-account quantum — the sums demandable, and the account that survives scrutiny
  • DSU / delay-to-revenue quantum — lender-grade delay-in-start-up loss modelling

Forensic Products — Delivery & Delay

  • Disruption and lost-productivity quantum on measured-mile methodology
  • Acceleration and recovery cost quantum — including constructive-acceleration record assessment
  • Differing site conditions quantum from tender-record and encounter-record analysis

Professional-Negligence Adjudication Support

  • Where a construction professional faces adjudication: support runs from PI-notification discipline at the Notice of Adjudication through defence analysis
  • The modern exposure, named at practice level — an adjudication provoked by a professional's default can return as a damages head in later proceedings, so the defence file is built for both forums at once
  • Insurer and panel-solicitor coordination supported; notification and coverage questions themselves sit with the client's broker and legal advisers
Fees — strictly non-contingent.Expert work is excluded from every conditional arrangement: time charges plus a fixed report fee agreed on scoping, hearing attendance by the day. No Stage 1 gateway — conflict check within one working day.See the Fee Schedule →
Methods, stated and maintained.Forensic work is performed to the current published protocols — the SCL Delay & Disruption Protocol (2nd edn), AACE 29R-03 forensic schedule analysis and 25R-03 lost productivity, CIOB planning protocols, and DCMA-14 schedule-quality screening — with measured-mile and earned-value productivity methods, and recognised industry productivity datasets where appropriate. Maintained against current editions; protocols are named, never reproduced.
At a glance

Why Quantico for expert work

  • Forensic analysis of project finances and scheduling
  • Independent expert evidence — duty to the tribunal, CPR 35 / CIArb compliant
  • Named expert CV available on request, with conflict check in one working day
  • EVM implementation and variance reporting

Instruct an independent expert

Tell us the forum, the form of contract and where the matter stands. A view and a next step within one working day — enquiries handled in strict confidence.

Instruct an independent expert  →
Statutory Adjudication

Pay now, argue later.
Be ready for both.

Statutory adjudication under the Construction Act 1996 resolves construction disputes in as little as 28 days — and the decision binds until finally determined by litigation in the Technology and Construction Court, arbitration, or agreement. Whether you are chasing a notified sum or defending one, the outcome usually turns on work done long before the Notice of Adjudication is served. That is where Quantico sits.

In Plain Terms

Adjudication in ninety seconds

Every party to a construction contract has a statutory right to refer a dispute to adjudication at any time — before, during, or after the works. An independent adjudicator, appointed within seven days, decides the dispute within twenty-eight. The decision must be complied with immediately, and the TCC enforces adjudicators' decisions robustly by summary judgment, even where the adjudicator got the facts or the law wrong. Speed is deliberately given precedence over perfection: the right answer is subordinated to a fast one, and the merits can be revisited later.

Most adjudications are about money — and most money adjudications are about notices. Under s.111 of the Act, the payer must pay the notified sum by the final date for payment. If no valid Payment Notice or Pay Less Notice is served in time — by mistake, oversight, or otherwise — the payee's own application stands as the notified sum, right or wrong, and an adjudicator will order it paid in full. The industry calls this a "smash and grab"; the courts prefer payment notice dispute, because the referring party is simply enforcing a statutory right to cash flow. Whole payment positions turn on whether a notice stated the sum considered due, the basis of its calculation, was clearly labelled, correctly served, and landed within the prescribed period — and, increasingly, whether it reflected a genuine assessment rather than a placeholder.

If the contract's adjudication clause falls short of s.108 in any respect, the statutory Scheme replaces it wholesale. Payment clauses that fall short are patched only where deficient. Knowing which regime actually governs your contract — JCT, NEC4 Option W2, FIDIC as amended, bespoke rules, or the Scheme — is the first question in every dispute, and the one most often answered too late.

The Machinery

The payment cycle, mapped

Every compliant construction contract runs the same statutory machinery: a stated due date, a payment notice window, a pay less notice window, and a final date for payment. Miss a window and the notified sum crystallises. The standard forms are compliant out of the box — but their clocks run differently, and amendments routinely break them.

The "adequate mechanism" required of every construction contract — Housing Grants, Construction and Regeneration Act 1996, ss.110–111 (as amended).

JCT Design and Build

Unamended · default periods

Interim Valuation Date monthly · Contract Particulars Due Date Payment Notice Last day for Pay Less Notice Final Date for Payment Next cycle 7 days 5 days 14 days · due date → final date 5 days before final date Interim Payment Application

Interim Payment Application made by the Interim Valuation Date · due date 7 days later · Payment Notice within 5 days of the due date · final date 14 days from the due date · Pay Less Notice not later than 5 days before the final date.

NEC4 Engineering and Construction Contract

Unamended · default periods

Starting Date Assessment Date monthly assessment interval Due Date PM certifies payment Last day for Pay Less Notice Final Date for Payment monthly interval 7 days 21 days · due date → final date 7 days before final date Application for Payment before the Assessment Date

Application for Payment submitted before the Assessment Date · Project Manager certifies and payment becomes due 7 days after the Assessment Date · final date 21 days from the due date · Pay Less Notice not later than 7 days before the final date.

Default, unamended positions shown for orientation — always verified against the executed contract, its amendments, and the Scheme where provisions fall short. Quantico builds these calendars, per contract and per supply-chain tier, as part of notice architecture.

Before the Merits

Jurisdiction: where adjudications are won and lost

Without jurisdiction, an adjudicator's decision is a nullity and the TCC will not enforce it. With it, the courts enforce robustly — even where the adjudicator got the facts or the law wrong. The Adjudication Society and CIArb Construction Adjudication Practice Guideline distils threshold jurisdiction into a checklist every referring party should clear before serving notice — and every responding party should test on receipt.

The threshold checklist

  1. Is there a binding contract — and when was it entered into?
  2. Is it a construction contract for construction operations (ss.104–105)?
  3. Do any exclusions bite — process plant, supply-only, residential occupier (s.106), territorial scope?
  4. Has a dispute crystallised — claim made, considered, and not admitted?
  5. Is one dispute referred, or several without consent?
  6. Are the adjudicating parties the contracting parties?
  7. Was the appointment made strictly per the contract or the Scheme?
  8. Has the same, or substantially the same, dispute already been decided?

Referring well

The referring party's discipline mirrors the checklist: crystallise the dispute before notice — claim made, considered, and not admitted; scope the Notice of Adjudication tightly, because it defines the adjudicator's jurisdiction; refer one dispute; appoint strictly per the contract or the Scheme; and assemble the evidence before the notice is served, so the seven-day window works for you, not against you.

Before any referral spend: clear the jurisdiction threshold screen — construction contract, construction operations, crystallised dispute — and sequence true-value strategy correctly where a notified sum is in play.

On the receiving end

A responding party who doubts jurisdiction has a strategic choice: refuse to participate, participate while expressly reserving its position, refer the point to the court, or waive the objection and proceed. The safest course is usually to participate under a clear, early, and specific reservation — preserving the challenge for enforcement.

The trap: participate fully without reserving your position and you may confer jurisdiction by conduct, losing the objection entirely at the enforcement stage. Reservation discipline in the first response is not a formality — it is the challenge.

Professionals: notify PI insurers on the Notice of Adjudication — not the decision. Notification clauses commonly bite at the notice, and leaving it until the decision risks the cover the defence depends on. Confirm the position with your broker the same day the notice lands.

Where an adjudicator strays beyond the notice, fails to consider a properly raised defence or set-off, or decides a matter already bound by a prior decision, the decision — or the severable part of it — will not be enforced. Scoping the Notice of Adjudication and testing it against this checklist is a quantity surveying and commercial exercise as much as a legal one.

How the Law Moved

The payment notice dispute, in three acts

A decade of TCC and Court of Appeal authority reshaped what a missed notice costs — and what can be done about it afterwards. Three cases tell the story, with Harding v Paice [2015] EWCA Civ 1231 as the bridge: the Court of Appeal held that a final account could always be re-valued in a further adjudication despite missing notices, and expressly left open whether the interim-payment cases were rightly decided. Coulson J answered that question in Grove.

Act I · The deemed agreement

ISG Construction v Seevic College

[2014] EWHC 4007 (TCC)

An employer served neither a Payment Notice nor a Pay Less Notice against a £1.1m application. The court held the employer must be taken to have agreed the value stated in the application — and could not launch a second adjudication to establish the "true" value of the same interim application. The smash and grab era began.

silence against an application was treated as agreement of its value.

Act II · The pressure point

Galliford Try Building v Estura

[2015] EWHC 412 (TCC)

A vastly over-stated £3.9m "Indicative Final Account" application met no valid notice. The court enforced the decision but — exceptionally — stayed execution above £1.5m to avoid manifest injustice, exposing the strain in the Seevic logic: if the value was truly "agreed", why stay any of it?

the courts flagged the injustice, but only a rare partial stay relieved it.

Act III · The reset

S&T (UK) v Grove Developments

[2018] EWHC 123 (TCC); upheld [2018] EWCA Civ 2448

On a £14m application served just after practical completion — where the interim cycle could no longer self-correct — the court held Seevic, Estura, and Kersfield wrongly decided: the notified sum must be paid first, but the payer may then adjudicate the true value of the application as a separate dispute, with any overpayment repaid. A second adjudication runs in strict sequence; it can never act as a Trojan horse to avoid paying. The case is also the leading authority on Pay Less Notice validity — sum due, basis of calculation, judged as a reasonable recipient would read it.

pay the notified sum, then fight the true value — in that strict order.

Since Grove — where the courts now stand

  • Pay first is absolute. The notified sum must actually be paid before a true-value adjudication is pursued — there is no racing for a valuation decision (M Davenport Builders v Greer [2019]; reconfirmed VMA Services v Project One London [2025]).
  • Substance over form. An unlabelled document can be a valid payment notice if it states the sum due and the basis of calculation — but one document cannot do duty as both notices; serve them as two distinct instruments (Placefirst v CAR Construction [2025]).
  • No re-characterisation. A late payment notice cannot be rebadged afterwards as a pay less notice — labelling and timing both bind (Vision Construct v Gypcraft [2025]).
  • Not overly prescriptive. A pay less notice withholding down to £0 with stated reasons stands; the courts won't dissect competent notices on contrived grounds (RBH Building Contractors v James [2025]).
  • Genuine assessment. A placeholder figure pending "a further notice" is not a statement of the sum considered due (Downs Road v Laxmanbhai [2021]) — an argument now raised with increasing frequency.
  • Insolvency is no bar. The right to refer a payment notice dispute survives the referring party's liquidation, though enforcement may be conditioned (Bresco v Lonsdale [2020] UKSC 25).
How Quantico Helps

Contract · Cost · Time

Adjudications are won on preparation, not eloquence. Quantico provides senior commercial, quantum, and delay expertise across the full adjudication lifecycle — from notice discipline months before a dispute crystallises, through referral or response support, to true-value proceedings after payment. Capability is stated at practice level; every engagement is conflict-checked and confidential.

Contract

Getting the regime right

  • Payment and adjudication clause compliance reviews against ss.108–111 and the Scheme — JCT, NEC4 W2, FIDIC-administered and bespoke forms
  • Notice architecture: due-date and final-date calendars, template discipline — always serve (£0 if that is the assessment), label clearly, serve per the contract, keep Payment and Pay Less Notices as distinct instruments
  • Dispute crystallisation strategy and Notice of Adjudication scoping — the notice defines the adjudicator's jurisdiction
  • Threshold jurisdiction audits and challenge strategy — construction operations, hybrid contracts, crystallisation, serial-dispute overlap, and reservation-of-rights discipline, aligned to the Adjudication Society / CIArb Practice Guideline

Cost

Quantum, defended or advanced

  • Interim and final account build-ups robust enough to stand as the notified sum
  • True-value adjudication quantum — post-Grove valuations commenced promptly once the notified sum is paid, so recovery isn't parked until the final account
  • Abatement and set-off analysis: defect valuations, cross-claims, and liquidated damages positions
  • Forensic quantum analysis of variations, loss and expense, and prolongation costs to adjudication timetables

Time

Delay, evidenced properly

  • Extension of time analysis supporting — or dismantling — delay damages deductions in Pay Less Notices
  • Forensic schedule analysis compressed to adjudication timescales without losing rigour
  • Concurrency, prevention, and time-at-large positions framed for a 28-day tribunal
  • Serial adjudication strategy where successive EOT disputes must not repeat "the same or substantially the same" dispute
Instructing Quantico

Two ways in — both fast

For employers, contractors & subcontractors

Direct support at any stage: pre-emptive notice audits while the project is live, rapid referral or response preparation once a dispute crystallises, and quantum or delay analysis for true-value proceedings after a notified sum has been paid. The seven-day and twenty-eight-day clocks reward parties whose evidence is assembled before the notice is served — engage early and the timetable becomes your advantage, not your opponent's.

Conflict check within one working day

For instructing solicitors

Independent quantum and delay input for adjudication, TCC enforcement, and subsequent final determination — prepared to the standards expected of expert evidence under CPR Part 35 and the CIArb protocol, so analysis produced under adjudication pressure survives into litigation or arbitration without rework. Practice-level engagement, no client or project identification in marketing materials, ever.

Conflict check within one working day
The fee route, in one line.Free 20-minute triage call → £1,750 Stage 1 merits report within ten working days → “no win, low fee”, fixed-fee low-value track, or traditional retainer as the merits support. Solicitor instructions for expert work bypass Stage 1 via the conflict check.See the Fee Schedule →

Low-value disputes are viable too

For disputes up to £100,000, the CIC Low Value Disputes Model Adjudication Procedure (RICS-supported) and the ICE Payment Notice Dispute procedure cap the adjudicator's fee by reference to the sum in dispute — making recovery of a modest notified sum economic where a conventional adjudication would not be. Referrals under the CIC procedure rose sharply through 2025. Quantico prepares proportionate, fixed-scope referrals and responses matched to these procedures — on the fixed-fee low-value track: £3,500 – £6,500 for claims of £10,000 – £100,000, with the adjudicator's fee capped on a published sliding scale of £2,000 – £5,000 for disputes under £100,000.

Quantico acts as commercial adviser, party representative, or independent expert — but never in combined roles on the same matter. Independence and the duty to the tribunal are preserved from first instruction.

Framework & leading authorities

  • Housing Grants, Construction and Regeneration Act 1996 ss.104–117 (as amended by the LDEDC Act 2009)
  • Scheme for Construction Contracts SI 1998/649 (as amended 2011)
  • ISG v Seevic College [2014] EWHC 4007 (TCC)
  • Galliford Try v Estura [2015] EWHC 412 (TCC)
  • Harding v Paice [2015] EWCA Civ 1231
  • S&T (UK) v Grove Developments [2018] EWCA Civ 2448
  • M Davenport Builders v Greer [2019] EWHC 318 (TCC)
  • Bresco v Lonsdale [2020] UKSC 25
  • Placefirst v CAR Construction [2025] EWHC 100 (TCC)
  • VMA Services v Project One London [2025] EWHC 1815 (TCC)
  • Carillion v Devonport Royal Dockyard [2005] EWCA Civ 1358
  • TCC adjudication enforcement (CPR Part 24 summary judgment)
  • Adjudication Society & CIArb, Jurisdiction of the UK Construction Adjudicator, Practice Guideline (3rd ed.)
  • CIC Low Value Disputes MAP (2nd ed.) & ICE Payment Notice Dispute MAP
The next step

Ready when the clock starts. Better before it does.

  • Proactive — notice architecture and payment-cycle calendars reviewed before the next application lands
  • Prompt — referral or response support mobilised inside the seven-day window
  • Sequenced — true-value strategy commenced correctly once the notified sum is paid
  • Confidential — conflict check and a named view within one working day

Schedule an introductory consultation

Thirty minutes on your payment cycle, your notices and your options — whether the dispute is a risk on the horizon or a Notice of Adjudication on the desk. Call or book directly; enquiries handled in strict confidence.

Schedule an introductory consultation  →
Sectors & who we serve

Eighteen sectors — the full breadth, declared.

Whichever seat you hold, the offer is framed from your side of the contract.

Sectors

Whichever sector, the route in is by seat — the three doors above land on each persona's natural entry pages, conflicts checked within one working day.

Who we serve
Cross-lifecycle·Training

Training — the full topic menu

“Continuous professional development, tailored to your team.”

Seminars for all levels, delivered by senior practitioners. In-house programmes tailored to the client's specific needs. UK & GCC delivery; CPD-aligned.

Commercial & Procurement

  • Procurement
  • Commercial awareness
  • Valuation of variations
  • Contract & supply-chain administration

Contracts & Compliance

  • Contract awareness — JCT · NEC · FIDIC
  • Record keeping & notices
  • Construction Act 1996 essentials — payment & adjudication
  • Building Safety Act 2022 briefing
  • Adjudication update — the current case law
  • NEC4 ECC in practice — programme, early warning and compensation events

Planning, Risk & Performance

  • Project planning
  • Risk — identification to optimisation
  • Earned Value Management (EVM)
  • Schedule quality & analytics awareness

Claims & Disputes

  • Claims & dispute management
  • Dispute-avoidance techniques
  • Determinations & EOT assessment practice
  • The eleven heads of claim — naming, noticing, proving
  • Forensic delay analysis — the SCL Protocol and AACE method taxonomies
  • Arbitration & ADR after the 2025 Act and Churchill
  • FIDIC for GCC practitioners — with a mandatory-law session: delay damages, time bars, taking-over and decennial liability

Security, Insurance & Recourse

  • Bonds & security for performance — instruments, triggers, expiries
  • Construction insurance essentials — CAR / PII and the DE / LEG defect-exclusion tiers, with the client's broker in the room
  • Collateral warranties & third-party rights after Abbey Healthcare
  • Termination & insolvency in the supply chain — including CIGA 2020

NEC & FIDIC — the engineering-contract family

  • One discipline, two dialects — early warning ≈ advance warning (Sub-Clause 8.4, 2017); compensation event ≈ Claim / Variation
  • Project Manager ≈ Engineer as neutral determiner (Sub-Clause 3.7) — the determination disciplines compared
  • The programme as the instrument of record in both families
  • Time-bar cultures contrasted — NEC cl 61.3 (eight weeks) against FIDIC 20.2.1 (28 days)

Notices & determinations — NEC · JCT · FIDIC

  • The notice matrices, form by form — what, to whom, by when, in what form
  • Condition precedent or not — the drafting signals and the case-law tests
  • Determinations that survive scrutiny — reasons, records, the fair-assessment discipline
  • When the clock has run — the fallback positions, assessed honestly
Fees — fixed on scoping.Training days are quoted per day with materials, delivered on-site or remote, and fixed on scoping to the topic set and audience.See the Fee Schedule →
Fees & Engagement·Indicative fees — confirmed on scoping

Fees, stated plainly.

“Shared risk where the merits support it. Fixed fees where independence demands it. Small print you can actually read.”

Fees are published for business clients and are exclusive of VAT. Every figure is an indicative starting point from the value stated — subject to the initial discussion, the information available and the agreed scope, and confirmed on scoping. Quantico acts for business clients only — engagements are not accepted from consumers or from individuals contracting as residential occupiers. Every figure on this page is an invitation to treat, not an offer capable of acceptance — engagement is subject to Quantico's Standard Terms of Appointment and Service Agreement, issued with the Engagement Letter prior to appointment, and, for dispute work, the Stage 1 review. Further particulars are available on request, within one working day.

How engagement begins

Triage first. Evidence second. Fee route third.

1 · Free triage call — 20 minutesIs the claim worth pursuing at all? Obvious non-starters are told so at no cost. Triage and scoping only — advice on the merits follows the Stage 1 review.
2 · Stage 1 Initial Review — £1,750 fixed, in advanceYour evidence file assessed; a written merits & eligibility report within ten working days of a complete file. 50% credited against the first invoice if retained under Proposal A or C within 30 days.
3 · The fee route offered“No win, low fee”, fixed-fee mediation, or a traditional retainer — as the merits support. The Stage 1 review is the gateway to Proposals A–C.
Solicitors — straight to conflict checkExpert instructions (Proposal D) bypass Stage 1: conflict check within one working day, then a scoping call. See Expert Services.

One condition sits above all others, in plain terms: your prospects depend on the evidence file you provide — comprehensive, and logically and chronologically structured. A file-structure template is issued on instruction. The Stage 1 report covers the contractual position, a notice-validity audit, quantum shape, a heads-of-claim triage — the head named, the machinery identified, the notice position and record set checked — a jurisdiction threshold screen for adjudication matters (construction contract, construction operations, crystallised dispute) before any referral spend, a security & insurance response screen (bonds and PCGs held, triggers live, PI / CAR notification status), limitation check and opponent solvency screening, a recommended dispute route, and the fee route(s) Quantico is prepared to offer.

Proposal A — dispute recovery

“No win, low fee” adjudication retainer

Available only where the Stage 1 review confirms eligibility. Quantico shares your risk; it does not buy your claim. Any uplift is calculated on Quantico's base fees only — never on, or by reference to, the amount you recover.

ElementBasis
Ongoing fee — payable monthly, win or lose50% of Rate Card rates for work performed
Deferred balance — payable on SuccessThe remaining 50% of Rate Card rates
Success fee — payable on SuccessAn uplift of 25–50% on Quantico's base fees only

Smash-and-grab fixed price

  • Where Stage 1 confirms a clear payment-notice default: £4,500 plus 5% of the sum referred between £10,000 and £100,000, plus 2% above £100,000 — the percentage keyed to the sum referred, not the sum recovered
  • “No win, low fee” variant: half payable on referral, the balance plus a 50% uplift on Success
  • What the base fee buys: the payment-notice audit, quantum verification and the referral are produced by the same QS-led team — no external quantity surveyor's fee layered on top as a disbursement

Low-value track — capped-fee procedures

  • Claims of £10,000 – £100,000 referred under the CIC Low Value Disputes Model Adjudication Procedure (2nd edition) or TeCSA's low-value procedure: fixed fee £3,500 – £6,500, agreed from the Stage 1 review
  • The adjudicator's fee is capped on a published sliding scale — £2,000 to £5,000 by value for disputes under £100,000 — making modest notified sums economic to recover

Eligibility & “Success”

  • Ordinarily: sum in dispute £25,000 or more (£10,000 or more where a capped-fee low-value procedure applies); an opponent with verifiable assets or covenant strength in England and Wales; contemporaneous records; a claim within limitation
  • “Success” means any financial benefit obtained in connection with the dispute, in money or money's worth — a decision in your favour, any payment or settlement, withdrawal or reduction of a counterclaim or deduction, release of retention, or any other benefit. It operates solely as the event on which the deferred balance and uplift fall due; it never converts the fee into a share of the recovery
Proposals B · C · D

Mediation. Retainer. Expert.

B — Mediation & conflict avoidance

  • Fixed fee, non-contingent — outcomes at mediation are consensual and the pricing reflects that
  • Position statement, quantum pack and mediation bundle: fixed from £3,500, agreed from the Stage 1 review
  • Attendance at mediation or CAP session: £1,950 per day or part; post-settlement drafting support with your solicitors at Rate Card
  • Courts now have the power to order parties into ADR — early mediation frequently resolves disputes at a fraction of adjudication cost, and Proposal B may be combined with Proposal A where adjudication follows

C — Traditional retainer

  • A conventional professional appointment for employers, developers, funders and monitoring contexts — cost certainty, monthly reporting, complete independence from outcome
  • Fixed or capped fee agreed at the outset by reference to project value and the sum in dispute — envelopes from £12,500, confirmed on scoping
  • Above £5m in dispute: bespoke — typically a percentage of the sum in dispute, payable irrespective of outcome, staged against deliverables
  • No element of the fee is contingent — appropriate where governance, funding covenants or audit requirements preclude conditional arrangements

D — Expert witness retainer

  • Strictly non-contingent, always — the courts and RICS professional standards prohibit success-related fees for testifying experts, and this retainer is excluded from every conditional arrangement
  • Time charges plus a fixed report fee agreed on scoping, by reference to quantum and delay complexity; hearing attendance by the day
  • No Stage 1 gateway — conflict check within one working day, then written scoping
  • The expert's duty is to the court or tribunal and overrides any obligation to those instructing or paying — see Independence, stated plainly
Proposal E — outside the dispute

Ready when the clock starts. Better before it does.

Non-contentious, non-contingent, and available without the Stage 1 gateway — the advice that prevents the dispute, not merely the representation that fights it.

E1 — Funder due diligence & monitoring

  • Initial commercial appraisal fixed by project value, from £6,500; monthly drawdown monitoring from £1,750 per month

E2 — Commercial maturity assessment

  • Scored maturity matrix with a prioritised remediation roadmap — fixed from £7,500 by organisation and portfolio size

E3 — Risk management

  • Risk registers, contract risk-allocation reviews, contingency and QSRA challenge — fixed by scope or day rate, confirmed on scoping

E4 — Pre-contract & procurement

  • Tender design review, evaluation frameworks, schedules of amendments, appointment and warranty reviews — fixed per document or package, from £2,500

E5 — Contract, payment, security & insurance-clause health checks

  • £3,500 fixed per contract — notices, payment-mechanism compliance with the Construction Act, application and certification hygiene, set-off exposure, the security schedule (bonds, PCGs, retention and advance-payment instruments) and insurance-clause conformity — clause-level review only; placement and coverage sit with the client's authorised broker
  • Post-adjudication limitation line — rights following an adjudication decision tracked: the final-determination window and the repayment-claim clock, so a temporarily binding decision is never left to harden by inattention
  • BSA historic portfolio limitation review — the 30-year retrospective horizon mapped across the portfolio, with a record-retention protocol to match

E6 — Training

  • Contract administration, payment-cycle discipline, notices, records and claims-awareness workshops — day rate and materials confirmed on scoping, on-site or remote
Retained advisory optionMonthly commercial support from £2,950 per month (two consultant days) — priority access across E1–E6, quarterly maturity re-scoring, reduced Rate Card for overflow. Twelve-month initial term, then rolling quarterly.

Hourly and day rates are confirmed on scoping and fixed for the engagement. The full Rate Card is available on request.

The small print

Read before you rely on any figure above.

Basis of publication. All figures are exclusive of VAT and are indicative starting points from the value stated — subject to the initial discussion, the information available and the agreed scope — pending confirmation in the Engagement Letter. This page is a proposal framework and an invitation to treat, not an offer capable of acceptance; no contract arises until Quantico issues, and you accept, an Engagement Letter to which the Standard Terms of Appointment and Service Agreement are attached, issued prior to appointment. Those documents contain the entire agreement: nothing on this website forms part of any contract or is to be relied on as a representation, and if anything on this page conflicts with them, they prevail. Quantico acts for business clients only — engagements are not accepted from consumers or from individuals contracting as residential occupiers, and the Terms contain a warranty to that effect on which Quantico relies. The Stage 1 fee is payable in advance and is non-refundable once the review has been completed; any credit applies as stated in the Engagement Letter.

The evidence file. Every merits assessment, submission and fee offer depends wholly on the evidence file provided, and on its completeness, accuracy, authenticity and provenance, which you warrant — including disclosure of matters adverse to your position. Prospects of success depend on comprehensive, complete evidence, logically and chronologically structured and indexed — the contract and all amendments; payment applications, payment notices and pay less notices with dates of service; programmes and progress records; variations and instructions; correspondence; and any adjudication, settlement or without-prejudice history. A file-structure template is issued on instruction. The compressed adjudication timetable makes the time limits notified for instructions, documents and approvals essential, and late or altered instructions are at your risk. Deficient, false, misleading, materially incomplete or late material voids any assessment, is a Payment Event on which fees for work performed fall due at full Rate Card rates, and permits suspension or termination (clauses 4 and 10).

Adjudicator's fees — payable by you in all events. The adjudicator's and any nominating body's fees and expenses are your liability, owed jointly and severally with the other party, payable regardless of outcome and wholly outside every proposal above — unless a capped-fee low-value procedure applies and is stated in the Engagement Letter. Outside a capped procedure, adjudicators commonly charge £300+ per hour and total fees frequently reach £20,000 – £30,000. An adjudicator may apportion fees against you even where you are otherwise successful, and you bear the risk that a decision proves unenforceable while remaining liable for those fees under the adjudicator's own terms (clause 7).

No costs recovery in adjudication. Party costs — including Quantico's fees — cannot be recovered from the opposing party in adjudication. Statutory interest and fixed-sum compensation on qualifying commercial debts are claimed as part of your substantive entitlement where applicable; your fees under these proposals are paid by you, from your recovery where a conditional basis applies. Disbursements — nominating fees, independent experts, counsel, mediator fees, venue hire and similar — are payable by you regardless of outcome and may be required in advance.

Conditional fees — how they work, and what they are not. Any success fee is an uplift calculated on Quantico's base fees only and is never determined by reference to the amount recovered; “Success” operates solely as the event on which payment falls due, not as a measure of any fee, and nothing on this basis is a damages-based agreement. You remain free at all times to settle or discontinue. Settling, compromising or abandoning the dispute without Quantico's prior written agreement to the fee consequences, failing to cooperate or to provide instructions or funds within 14 days of written request, providing false, misleading or materially incomplete information, and insolvency are Payment Events — agreed events, not breaches — on which Rate Card fees for all work performed fall due as a debt (neither damages nor a penalty), together with any success fee already earned. Success is measured at the point of recovery: a later true-value determination or repayment is a separate matter and does not reduce fees earned; where the opposing party's insolvency prevents receipt, adjudicator's fees, disbursements and fees payable in any event remain due, with the conditional elements as stated in the Engagement Letter. If the engagement ends early, a Success achieved within 12 months in reliance on Quantico's work product triggers the deferred balance and any success fee (clauses 9, 10 and 13).

Invoices, funds and security. Invoices are payable within 14 days and, where the appointment is a construction contract for Construction Act purposes, each invoice stands as the payee's payment notice. Reasonable sums on account of fees and disbursements may be required before any stage, including before a referral is served; unpaid invoices or unfunded requests permit suspension of the services on seven days' written notice, with a remobilisation charge on resumption. Sums due are payable in full without set-off, are payable within seven days of receipt of any recovery, carry interest if late, and are secured by a charge over recovery proceeds limited to the sums due and a lien over papers; a director's guarantee may be required for corporate clients (clauses 5, 9, 11 and 13).

Expert evidence. Independent expert witness work is strictly non-contingent, excluded from every conditional arrangement, and procured on the terms of Proposal D or from an external independent expert as a disbursement. Where Quantico has acted as your claims consultant or advocate in the same dispute, it may decline the witness role and act instead as expert advisor behind your legal team, recommending a suitably qualified independent expert, to protect the weight of your evidence (clause 8).

Status, privilege, liability and enforcement. Quantico (L.A.W.) Limited is a specialist construction claims and commercial consultancy. It is not a firm of solicitors, is not regulated by the SRA, and does not conduct litigation; legal advice privilege does not attach to consultant communications and privilege in adjudication cannot be assured — take separate legal advice where privilege is critical. Enforcement of an adjudicator's decision requires court proceedings conducted by solicitors; Quantico will introduce its solicitor panel, and that retainer is separate and yours. Quantico does not advise on or arrange insurance or litigation funding and signposts authorised providers only. Quantico gives no warranty as to the outcome of any dispute, and its liability is limited as set out in clause 14 of the Terms, capped by reference to its professional indemnity cover — insurer details and territorial coverage available on request. Advisory deliverables are provided for the instructing client alone and may not be relied on by any third party without written consent.

Acceptance discretion. All proposals are subject to the Stage 1 review (Proposals A–C), Quantico's underwriting criteria, capacity and conflict checks; Quantico may decline any instruction, without giving reasons, or offer an alternative proposal, and the engagement may be reviewed where the claim's prospects or the opposing party's financial covenant materially deteriorate (clause 13.2). Where the underlying contract in dispute is with a residential occupier, the statutory right to adjudicate does not apply and any adjudication depends on that contract's own terms — this forms part of any merits assessment. The worked illustration above demonstrates the fee arithmetic only and is not a prediction of outcome; no outcome is promised anywhere on this site.

Further particulars. The full fee proposal and the Rate Card are issued with the Standard Terms of Appointment prior to appointment, and all three are available on request — info@quantico.law — with a response within one working day. See also Legal & Regulatory.

Start with the triage call

Twenty minutes, no fee, no obligation — is the claim worth pursuing, and which route fits? Triage and scoping only; advice on the merits follows the Stage 1 review of your evidence file.

Book the free triage call  →

Instructing solicitor? Conflict check within one working day →

Contact us·Schedule the introductory consultation

Contact — one action, zero friction.

“Tell us where the project is — preconstruction or post contract — and where you need an opinion. A professional opinion to help guide your strategy.”

Schedule a free 20-minute triage call directly, call +44 (0)330 229 7990, or write to info@quantico.law. UK · Ireland · EU · GCC · Canada coverage. Enquiries handled in strict confidence.